T - Sep 1 | Introduction Cryptography | HW #1 | ||
Th - Sep 3 | Block ciphers | - | ||
T - Sep 8 | AES | HW #2 | ||
Th - Sep 10 | Block Cipher Modes | - | ||
F - Sep 11 | - | - | Project 1 (AES) | |
T - Sep 15 | Cryptographic Hash Functions | HW #3 | ||
Th - Sep 17 | MAC | - | ||
F - Sep 18 | - | - | Project 2 (Hash Attack) | |
T - Sep 22 | Public Key Cryptography | HW #4 | ||
Th - Sep 24 | DH | - | ||
F - Sep 25 | - | - | Project 3 (MAC Attack) | |
T - Sep 29 | RSA | HW #5 | ||
Th - Oct 1 | RSA | - | ||
F - Oct 2 | - | - | Project 4 (Diffie-Hellman) | |
T - Oct 6 | Digital Signature | HW #6 | ||
Th - Oct 8 | Certificates | - | ||
F - Oct 9 | - | - | Project 5 (RSA) | |
T - Oct 13 | Exam Review | No Homework | ||
Th - Oct 15 | No Class | - | ||
F - Oct 16 | - | - | Exam 1 | |
T - Oct 20 | Secure Email, TLS | HW #7 | ||
Th - Oct 22 | TLS | |||
F - Oct 23 | - | - | Project 6 PGP and S\MIME | |
T - Oct 27 | Buffer Overflow | HW #9 | ||
Th - Oct 29 | Stack Smashing | - | ||
F - Oct 30 | - | - | Project 7 (TLS) | |
T - Nov 3 | Exam results | HW #10 | ||
Th - Nov 5 | Integer Overflow | - | ||
F - Nov 6 | - | - | Project 8 (Buffer Overflow) | |
T - Nov 10 | Passwords | HW #11 | ||
Th - Nov 12 | Passwords, SSO, Multi-Factor Authentication | - | ||
F - Nov 13 | - | - | Project 9 (Buffer Overflow) | |
T - Nov 17 | Software security | HW #12 | ||
Th - Nov 19 | Software security | - | ||
F - Nov 20 | - | - | Project 10 (Password Cracking) | |
T - Nov 24 | No Class - Friday Instruction | - | - | |
T - Dec 1 | Software security | HW #13 | ||
Th - Dec 3 | Exam Review | - | ||
F - Dec 4 | - | - | Project 11 (Extracting Secrets) | |
T - Dec 8 | Exam 2 In Class | - | Exam 2 | |
Th - Dec 10 | Social Engineering | - | Project 12 (Bombs) Extra Credit | |
Thu Dec 18 | 3 hours in Testing Center, Mon Dec 14 12:00 PM to Friday Dec 18 9:00 PM | - | Final Exam |