Introduction

I needed a better sense of my own velocity and accuracy at estimating deadlines. So I decided to go with an AGILE development methodology with 2-week sprints.

S1: Prometheus [May 2 - May 14]

  • [Milestone]: Level Analysis Complete

S2: Hyperion [May 16 - May 27]

  • [Milestone]: First-Stage Level Generation Complete (the methods taken here were scrapped – must re-do them)

S3: Tethys [May 30 - June 10]

  • [Milestone]: First-Stage Level Generation Complete

S4: Pandora [June 13 - June 24]

  • [Milestone]: Second-Stage Level Generation Complete

S5: Mimas [June 27 - July 8]

  • [Milestone]: Third-Stage Level Generation Complete

S6: Calypso [July 11 - July 22]

  • [Milestone]: Full Paper Draft Complete (sans final validation results)

S7: Iapetus [July 25 - Aug 5]

  • [Milestone]: Full Paper Complete with Validation Results

S8: Tethys [Aug 8 - Aug 19]

  • [Milestone]: Final Revisions Complete

S9: Atlas [Aug 22 - Sep 9]

  • [Milestone]: Schedule Thesis

S10: Titan [Sep 12 - Sep 23]

  • [Milestone]: Defend Thesis
mind/atlas-roadmap.txt · Last modified: 2016/06/03 06:34 by martindm
Back to top
CC Attribution-Share Alike 4.0 International
chimeric.de = chi`s home Valid CSS Driven by DokuWiki do yourself a favour and use a real browser - get firefox!! Recent changes RSS feed Valid XHTML 1.0